CSLR Progress 2

Home
Up

The story of the CSLR so far.....................

Milestones and see the map. Click on the pictures for larger images.

August 2003    -    Concrete Viaduct

September - December 2003    -    Leaves......

March 2004 - Workshop Corner

March - June - Progress on Engineer

July 2004 - Lifting The Bridge


August 2003

The viaduct I wanted to make involved casting concrete for the three arches and a bridge section which was easily removable for access. I made moulds, fixed in place using hardboard and wood. I then mixed the concrete in my wheel barrow and began pouring into the moulds, which promptly collapsed!

Rough Casting!Realising I now had only about 30 minutes to recover from a barrow full of concrete, I rebuilt and supported the moulds before refilling. The results two days later were somewhat rougher than anticipated, but have been given a rendering of cement, brushed on to fill the voids in the concrete.

Bambrough and passenger train cross the viaduct.Undeterred (!), I have made a temporary bridge section from some softwood in order that I can lay track over the top. This picture shows Bambrough with a passenger train going over the newly laid rails.

Back to Top


 

September to December 2003    -    Leaves on the Line

This period has been hampered by many things - leaves being one of them. This year was very dry, the trees holding on to their leaves right until the last moment, then dropping the lot very late. I seem to have spent hours trying to keep the running rails clear, let alone make any progress. However, the viaduct is starting to weather nicely, and I have begun construction of  the elevated wooden base for the next corner. This will hopefully have a spur into a storage area/engine shed/steam-up bay, as it is approximately 600mm above ground level and over a paved area.

The reduction in outside work has allowed progress on the loco's and stock, albeit in small but significant areas.

Back to Top


2004 - March    -    Workshop Corner

The beginning of the year progress has been halted every weekend by the onset of rain - or snow! Consequently, there was no advancement until March. A new workshop was constructed in the top corner of the garden in February and facilities installed therein to promote the running of the railway. This has allowed the separation of the railway from the garage and garden equipment, altogether a much more suitable environment for matters mechanical. The growth of last years planting however, continues apace!

Following the build of the workshop, the raised, high-level section of the line that crosses the doorway could be built. This has introduced another method of construction into the line, baseboard type trackbase from 12mm marine ply, onto similar T-section and plastic drainpipe supports. This leads into a long straight(ish) run down the opposite side of the pond built using decking timbers, again in a T-section and supported on bricks. This length is arranged on a falling gradient of around 1 in 80, to terminate at the same level as the lines beginning.

There is a spur leading to the workshop, but not into it at present. This is probably to be the steam-up area, since it is handy for the facilities and raised from the ground somewhat.

A difference of height was apparent where Lower Willow Tree station of about 40mm has meant that the loop there is presently lifted until suitable material is available to correct this. The point at the south end of the loop was also part on a slope, part flat and was believed to be the cause of some derailments. Due to the connection of the two ends of the line being imminent, this point has been lifted and will replaced further towards the north, as part of a cross-over to permit turning the engines and their trains.

Back to Top


Progress on 'Engineer'

A new welded bridge has arrived to replace the temporary structure, but most progress has been made on the build of No.8. See here for details and here for video.

Back to Top 


Lifting the Bridge

During July, apart from the work on Engineer, the liftout bridge has been fitted in place and it does actually lift out! The temporary wooden structure has been replaced by an all steel welded representation of an arch bridge. The butresses needed to be built up with treated wooden blocks to ensure the correct height and seating for the new bridge, the track length slightly altered and a new piece cut to fit the new bridge which is slightly longer than the old one. There are currently no other fixings to hold the bridge in place save for its own weight, but some rail clamps will be ordered to made the track connections good. This should be sufficient to hold the bridge in place. Test running has shown it does not move in use, but the accuracy of the track joints would be improved with a good fixing. Now what is needed are some retaining walls for the top of the viaduct sections and a brickwork representation on the sides.


Home | Southdown Railway Co | Clubs & Links | Along the Line | Locomotives | Rolling Stock | Feedback | Search

 Copyright CSLR Management. Made in England
For more information or questions regarding this web contact the driver/navvy/director!
Last updated : Thursday May 08, 2008