CSLR Progress 1

Home
Up

The story of the CSLR so far.....................

Milestones and see the map. Click on the pictures for larger images.

March 2002    -    Moved In!

April 2002    -    Pond Construction

June 2002    -    Bridge Installation

August 2002    -    Tunnel Cut-and-Cover

March 2003    -    Forging Ahead at Quarry Curve

April 2003    -    Woody Beach appears

May 2003    -    Hi-Level Stretch

July 2003   -    Bridging the Great Divide

August 2003 Onwards.......

 

 


March 2002

This is a picture of the garden before we got here - estate agents eye view!

   


 

April 2002

We really needed a pond since the goldfish we brought just weren't happy in the lined packing case they were in! Since a railway was in the design right from the start, we took the opportunity to build the first part of the line around the new pond.

You can see the 'raw' concrete (Celcon) blocks in the foreground here, these will form the track bed when finished.

Here, with the track in place, you can see the log edging going in, the space around the blocks will be filled and topped with ballast when everything has settled.

Back to Top


 

June 2002

A bridge was ordered from Peter Howarth of Garden Railway Structures, initially to re-cross the pond, but following it's arrival it was decided it was more suitable for a path crossing. Additionally, this allowed extension of the useable track into the next section of garden.

The bridge is not rigidly fixed in place, it sits on the bearing pads at each end and the track is fixed to it in two places. This is to allow the bridge to expand and contract according to the weather.

As supplied, the bridge arrives in it's natural aluminium state, but it was soon decided that it needed a coat of paint. Halfords car paints were used - a tin of Etch Primer gave a good key first, followed by standard grey undercoat/primer, then a blue top coat. Two full tins of blue were used to give as much protection as possible. The finish on the aluminium plate was marvellous!

Back to Top


 

August 2002

Tunnel mouths were picked up at the Reading show earlier in the year from Garden Railway Specialists. These are cast stone and rather to heavy and fragile for postage, but a phone call in advance of the show secured their arrival.

The tunnel mouths were placed in position at either end of a channel dug in the existing terrain. Previously laid concrete blocks form the trackbed for this section, more blocks are stood on end for the tunnel sides, thus preventing the earth from filling the channel. I used expanding foam in a can to hold everything in place, walls, ends, and finally using paving slabs for the roof. This means that the tunnel will easily hold the weight of anyone standing on it Concrete blocks turn out to be the perfect height for this structure, and the tunnel is (handily!) three blocks long, thus avoiding the need to cut them. It's also short enough to allow the removal of anything that may or may not be stuck in there.

Back to Top


March 2003

After a rest over the Christmas 2002 period, the wild undergrowth was cleared from the next area and once stable, 1.5 tonnes of Purbeck Stone and a maxi bag of builders sand arrived (at the wrong end of the drive!). Much transportation of stone and sand was followed by a build using the stone and some granite blocks recovered from the garden earlier.

A five foot radius curve was the aim, turning thro' 90 degrees and beginning to climb around the back of the patio (yet to be built). The raise in height is necessary to eventually pass over the already constructed tunnel.

The track will be laid on the granite blocks and some flatter stones, on a strong Rowland's mix (cement/compost/sand, applied dry and dampened later) which will resemble ballast and serve to take out the imperfections in the surface.

The track is bent to shape using a homemade device - bolts and r/c car bearings fitted to a small vice. Then the sleepers are slid back onto the LGB rail.

 

Back to Top

April 2003

Woody Beach progress - the decking has been installed and the blocks for the trackbed built around, levelling the area under the track with a weak cement mix. In this picture, you can get some idea of how far the track climbs from one side to the other.

 

In the picture left, is a view of the partly ballasted track with the Rowland's mix below and rough grit spread over the top too. To the left of the picture is the exit from the tunnel. In the picture right, you can see the entrance to the tunnel, over which the track will eventually return.

The extra rail required to reach Woody Beach arrived at Easter and (despite the rain, spending time with the family (!) and such like) the rail was bent and placed for 'clearance checks' by the end of the Easter holiday. This picture shows the track in place but not fixed. The spur into the back of the garage (to the right of the picture) leads to storage sidings in the garage, made up using LGB Radius 1 points and track. These are too sharp for most main line use, but are OK in this case.

Closer to completion, No.3 runs round the train following track levelling and partial ballasting. The point in the foreground is now the end of the line, until the bridge construction starts. Test runs with No.3 (manual control) shows that with the four heavy bogies in the picture, a suitable regulator setting will allow a complete out and return journey without touching, although slowing to a crawl on the last stage before Woody Beach and then rushing into the loop!

Back to Top

May 2003

The next stage is to cross the garden and over the top of the tunnel. So far, the undergrowth (denser than it looked!) has been cleared on the far side of the tunnel and a trench dug down to the clay. The bottom of the trench has granite blocks laid in and bedded to form the sub-base. The picture shows this to good effect, the present end of the line visible in the background by the signal box. Along the top of the granite blocks will be laid Celcon blocks on a bed of cement to ensure they are level. The line itself is level here and will be the highest point on the line.

This picture shows the gap to be bridged from the signal box to the tunnel roof. How it's to be done is at present undetermined! Several possibilities of bridge have been investigated, but it must have a curve and hopefully a central lift-out span to allow lawnmower access.

Back to Top

July 2003

I have now started to cross the great divide by putting in the main supports for my bridge section. The picture here shows only the main supports for either side of the lift-out section in place and some more raised base work at the tunnel end. I would like to put grasses over the tunnel eventually, so the area around will become embankment leading to the bridge. The lower track leading to the tunnel is on the right.


Home | Southdown Railway Co | Clubs & Links | Along the Line | Locomotives | Rolling Stock | Feedback | Search

 Copyright CSLR Management. Made in England
For more information or questions regarding this web contact the driver/navvy/director!
Last updated : Thursday May 08, 2008